Fri, 8 Nov 2024
22.7 C
Durban

Spires on Msikaba Bridge shoot skywards in elegant construction

Home Infrastructure Construction & Civils Spires on Msikaba Bridge shoot skywards in elegant construction

THE pylon spires of South Africa’s Msikaba Bridge mega project are on their way up, soon to tower almost 130 metres high at each side of the nearly 200m deep river gorge.

For Concor’s project director on this contract, Laurence Savage, this momentous phase will reveal the sheer grace of the Msikaba Bridge design, and the awesome scale of the development. The Msikaba Bridge forms part of the South African National Roads Agency Limited’s (SANRAL) N2 Wild Coast project and is being constructed by the CME JV, a partnership between Concor and MECSA, both 100% black-owned Grade 9CE South African construction companies.

Currently being slip-formed from the bifurcated legs of the pylons, each of the spires extends 95m from the bifurcation to the top of each pylon – taking the height of the bridge pylons to 128m.

“The inverted Y-shape of the concrete pylons is strikingly elegant, and will become a hallmark of this iconic structure – as the design is architecturally elegant, diverging from the foundation legs, up towards the bifurcation and symmetrically converging to the top of the spire,” says Savage. “This is the largest cable-stayed bridge to be built in South Africa, and probably one of the most complex engineering bridge projects yet executed in Africa.”

In this design, each pylon rests on two inclined legs which meet 21m from the start of the bifurcation which extends a full 11m. At 32m, the first section of the spire – starting with a diameter of six metres – is uninterrupted for 55,7m and comprises 14 slipform lifts. Then begins the inclusion of 17 anchor inserts over the next 35m of the spire, which reaches a height of 124m and will have converged to a four-metre diameter. These anchor inserts accommodate the 17 cables that run from the anchor blocks located behind each pylon to the spire, and then down to the 580 m-long bridge deck.

“To accomplish the lifts, we are using a jacking system for the formwork shutters, with eight jacks around the circumference of the spire,” he explains. “Each lift is 3,6m conducted at intervals of about two weeks per lift and we are making steady progress with quality and safety being paramount.”

The work is accessed using a specialised stair system, with one set of access stairs from ground level to the top of the bifurcation and a second stairwell to follow the shutter system up the spire. The formwork system comprises three decks that trail below each other; the interlinked decks lift together as the shutters are jacked up.

“The depth of the gorge – at around 197m – means that no work on the bridge deck itself can be done from ground level,” he continues. “Everything has to be done suspended from these two pylons – one on the south side of the gorge and one on the north side of the river.”

Like the leg of the bridge pylon, the reinforced concrete spire – with walls a metre thick – is hollow to reduce weight and is formed in a tubular design that significantly improves its strength-to-weight ratio. The reinforcing bar used in the spire includes 12 to 16 mm bar as lacing, with primary bars of 30 and 40 mm bar employed in high densities to carry the significant loads.

“Once the stays and bridge are in place, the load on each pylon will amount to around 7,000t,” he points out. The pylons are well advanced, with about half of the planned concrete volumes already poured by the top of bifurcation. After the last anchor insert, a four-metre parapet will be constructed around the very top of the pylon spire. Access to the inside of the pylon will be restricted to engineering inspections and maintenance.

“Indicative of the precision engineering being employed on this project is the number of activities that must take place at the same time – in a confined area,” Savage explains. “By the time we have completed the fifth anchor insert, for instance, we will have begun the launching of the first deck segment – followed shortly by the second and third segments. While these activities are taking place, the spire and inserts will continue to be erected and cast.”

Savage emphasises the intense focus on safety that has characterised the project, in line with Concor’s Zero Harm policy and protocols. Despite the high-risk site which has included excavations of up to 17m for the pylon anchors, the site team recently achieved 3,5 million Lost Time Injury Free hours. Preparation for working at heights is a particular priority, with specialised training mandatory for these activities.

“This is all part of a training regime around safety, where we are continuously conducting risk assessments with our workforce,” he says. “The first item for discussion every day on site is the safety of their working environment; our primary value is care – both for yourself and for others.”

Savage highlights that when the bridge deck commences launching across the gorge later in the year, the culture of safety – inculcated in all workers over the previous years of the project – will be second nature to all. This philosophy applies across the approximately 300 people working on the north and south banks of the bridge, with an additional 280 people currently engaged in various community and local upliftment projects in the vicinity and a further 80 people in the engineering team and laboratory support staff.

Intricate cable-stayed support

Each of the two bridge pylons has 17 anchor inserts, with each insert weighing 8 to 10 tonnes.  The inserts are constructed from structural steel and secure the cable stays in place at the top of the pylon. Each cable is made up of between 46 and 58 strand cables – with each stand cable containing seven strands. The rear cables run back to the two anchor blocks and those running to the front link into the bridge deck itself. The lowest strand cables feed to the deck segments closest to the bridge pylons, while the highest will link into the furthest deck segments mid-span of the bridge deck over the Msikaba River.

Most Popular

Sponsored News: Scope for private steam turbines to feed the grid – Weg Africa

STEAM turbines represent mission critical equipment for a range of industries from sugar and paper to steel and petrochemicals, and there is now greater...

Investment in EC cold storage facility boosts regional export capacity

COMMERCIAL Cold Holdings (CCH) has made a significant move to expand South Africa’s cold chain infrastructure by investing in CCH Greenbushes, a state-of-the-art commercial...

Regional development agency sells, leases and invests in diverse R1,4bn property portfolio

THE Eastern Cape Development Corporation (ECDC) is rolling out a R546 million refurbishment programme of its R1,370 billion property portfolio which it says is...

Supporting crop productivity for SA’s large- and small-scale farmers

OPINION | AGRICULTURE is synonymous with food production and, in South Africa especially, employment creation. But the sector’s importance extends into the socio-economic realm...