A 40 MW turbine generator from ArcelorMittal’s Vanderbijlpark works was repaired on a fast track schedule by Actom Turbo Machines.

The emergency repairs were required after the generator broke down in October 2018, with damage including failed bearings on the generator train. Details of the repair have just been released by Actom Turbo Machines, a division of Actom (Pty) Ltd, which had the generator back in operation by mid-December 2018.

The company first diagnosed all the elements that would require attention during the repair. All four bearings – as well as the rotor sealing elements – were found to be damaged. Other damage, which was unrelated to the October failure, was also discovered.

“The damage involved a crack on the high-pressure (HP) gland section of the main steam casing, while a second unforeseen irregularity was a malfunction in the starting or auxiliary oil pump,” said Danie Bloem, Actom Turbo Machines’ project manager on the contract.

Other irregularities were an incorrect bolt clearance on one of the HP palms, probably due to faulty installation.

“In addition to repairing the damaged bearings, we also had to recondition a spare set of bearings that ArcelorMittal had in reserve. The sealing segments were replaced with new ones manufactured at our Sasolburg works.”

Bloem said the process of repairing the crack in the main steam casing took the team five days, working around the clock. “A high level of welding expertise was required here, as the casing is made of a special material.”

The repair of the starting oil pump was also performed in only two days. This required the manufacture of a new shaft, and also the reconditioning of the mechanical seals.

Once the generator resumed operation, vibration testing confirmed that its performance had improved significantly, Bloem said.

According to ArcelorMittal, its Vanderbijlpark Works is one of the world’s largest inland steel mills and the largest supplier of flat steel products in sub-Saharan Africa.

Most Popular

SA’s new transmission company lays out ambitious grid plans

AT the official launch of the National Transmission Company South Africa (NTCSA) on Monday, 7 October, the company outlined the key focus areas developed...

R11.4bn development of off-grid EV charging stations launched in the Eastern Cape

ZERO Carbon Charge, in partnership with the Automotive Industry Development Centre Eastern Cape (AIDC-EC), together with the Eastern Cape Provincial Government, broke ground on...

Relocated carbon black oil tank farm starts operations

AFTER breaking ground in April 2022, Orion Engineered Carbons (OEC) officially unveiled its Tank Farm Project in Zone 7 of the Coega Special Economic...

SA’s chicken prices fuelled by ‘flawed’ regionalisation and heat treatment policies

OPINION | IRRATIONAL import bans on poultry, South Africa’s favourite source of protein, are inconsistent with global best practice, leading to unnecessary price inflation,...