CONCOR is carefully strengthening the structure on which the heavy new chillers will rest before upgrading Eastgate Shopping Centre’s heating, ventilation and air conditioning (HVAC) facilities for greater energy and water efficiency.

Concor contract manager Martin Muller explains that the HVAC system is located on top of a building on the centre’s roof parking area, in which tenants are active – and who need to continue trading during the renovation. Aside from the technical elements of the contract, therefore, clear and ongoing communication with the client and the tenants is a crucial aspect of success.

“The construction work includes the demolition of an existing roof, walls and slab above tenants,” says Muller. “The structure will then be strengthened to ensure it can safely carry the seven 10 tonne HVAC chillers which are to be installed on the rooftop building.”

Due to the presence of a tenant running a call centre in the adjacent building, demolition can only take place outside of normal working hours. He highlights the importance of Concor’s safety culture in ensuring safe working practices at night.

What is important is for the considerable load of the new installation to be effectively transferred into the centre’s existing concrete columns under the roof parking – and hence down into the foundations. This is being done through the construction of interlinking stub columns which will create a grid to support the chillers.

These columns are being cast systematically, working in a direction of priority for the HVAC specialists – so they can start their installations on the network of support steelwork and grating that Concor will provide.

The new structure will also include a transformer room and a perimeter louvre closure around the HVAC area. At about 3,5 metres high, the louvre will improve the rooftop aesthetics by concealing the installation from view. Concor’s team and subcontractors receive working-at-height training and work strictly according to safety protocols – especially since the HVAC rooms are 8,5 metres above ground on one side of the structure and 20 metres high on the other. Completing the project will be a steel roof, louvres to allow fresh air to cool the installation, access doors and a steel staircase.

Most Popular

Maximum compatibility and safety from new connections

WITH the new, optimised Nexus Connect flare connection, the Ingelfingen-based technology company Gemü is now introducing an innovative flare connection for its CleanStar and...

Powered grease gun a leap in lubrication innovation

SKF has launched its innovative TLGB 21 battery-driven grease gun that optimises lubrication efficiency and reduces costs by seamlessly combining advanced technology with a...

Donated tow tractor keeps Eastern Cape air ambulances flying

TO help save lives in the Gqeberha region of the Eastern Cape, the team at Toyota Material Handling, a division of CFAO Equipment, donated...

Real-time belt rip detection saves costs, reduces downtime and prevents injury

BECKER Mining has launched the newly developed BRS4.0 belt rip detection system, with advanced features for greater durability, higher efficiency and improved safety. Typical...